Project Details
Project Overview
- 222,314 m2 of partial depth asphalt removal
- Full depth removal of asphalt, including earth excavation, placing of Granular and 2 lifts of asphalt in a time restricted lane closure
- 900 mm diameter culvert replacement across 5 lanes of Highway 6
- 35,000 tonnes of S.P 19
- 24,180 tonnes of S.P 12.5
- 22,492 tonnes of Granular A
- Capital's staff of experienced workers and solid communication lead to success by maximizing efficiency in a time sensitive construction
- Job Challenges: accommodating multiple large production night paving jobs at one time...