Project Details
Project Overview
Facility improvements including an installation of a 200 millimeter diameter PVC watermain at the Cargil facility, in which we encountered unanticipated bed rock just below the surface and were required to break and remove it to a depth of 2 meters to safely install the watermain on time. Our forces worked around the clock to ensure there were no disruptions to the facility. All work was completed over one weekend to ensure all deliveries in and out weren’t disrupted.